Downtown Construction Progress

Construction work continued on the downtown streets in Hastings last week. After another week of work on the Riverfront Renaissance, crews completed all of the underground utility work within the intersection of Ramsey & 2nd Street, which included a reconfiguration of storm sewer pipes and a fire hydrant replacement. Before the Saturday Night’s Cruise-In, workers laid a portion of the gravel base material with temporary gentle ramp areas to accommodate the classic cars. Further work included removal and underground utility work within Olivers Grove. Surveying and layout work took place for the concrete curb and gutter that will be the next step.Keeping you up to date with the construction project as it proceeds. You can find a link to the city website at http://www.hastingsmn.gov/
   